Costs

Buying a 22 kW home EV charger

When a 22 kW home charger is real capacity and when it is an expensive badge on a single-phase house.

By Local EV Installers Editorial Team · Published · Updated

A 22 kW AC charger only delivers 22 kW if the car's onboard charger can take it and the property has a three-phase supply able to provide the current. Most UK homes are single-phase. On those supplies a 22 kW-labelled unit falls back to a much lower rate, often the same 7 kW class a cheaper, correctly specified charger would have given you. Buy the hardware for the supply you have, or get a network quote for three-phase before you buy the badge.

Cost planning notes for UK EV charger installation budgeting

The price effect of buying a 22 kW home EV charger

The unit can cost more, and the connection can cost much more again if the street cable changes. The running speed you wanted may never appear.

A miss that shows up later: buying a 22 kW home EV charger

The mistake is 'future proofing' a semi with a 22 kW post because a workplace had one. Workplaces often have three-phase already.

Write buying a 22 kW home EV charger into the quote

The quote should state the supply phase, the car's AC limit and the rate the installer expects to achieve, in kW, at your house.

Buying a 22 kW home EV charger

Some cars, including many plug-in hybrids and some smaller EVs, cannot use more than 7 kW or even 3.7 kW AC. A 22 kW wallbox does not change the onboard charger.

  • 22 kW needs three-phase and a capable car
  • Single-phase homes usually want 7 kW
  • The network quote comes first
  • Plug-in hybrids rarely benefit

Check buying a 22 kW home EV charger before you accept a price

Ask the distributor for the car's AC rate and look at your cut-out. If both are not in the 22 kW club, stop.

Frequently asked questions

Will the car charge on it anyway?

Yes, at whatever AC rate the car and the supply share. You may have overpaid for a label.

Is 11 kW the middle option?

11 kW is the common three-phase home rate for cars that support it. It still needs three-phase.

Can software unlock 22 kW later?

Software cannot invent a phase that is not in the cut-out.

Are public 22 kW posts the same kit?

They are AC posts on a commercial supply. Copying the model onto a house does not copy the supply.

Core buying guides

Start with these high-intent guides, then dig into the rest of the library.

Related guides

Sources and further reading

How this guide was prepared

This guide was written by the Local EV Installers Editorial Team. We compare official guidance, legislation and established consumer information, separate general information from project-specific advice, and show publication dates and sources. We do not accept installer accreditation claims at face value.

Read our full editorial policy.

Get a quote

Get EV charger installation quotes

Start with the installation postcode and service. Add optional detail only if you have it.

Free, no obligationSubmit the form at no cost. You decide whether to accept any quote.

Local introductionsWe pass your enquiry to installers covering the postcode. Reply speed and volume both vary.

No lead sellingDetails go only to relevant installers for quote contact. See the privacy notice.

Ask each company for OZEV status where relevant, competent-person membership and insurance. We introduce local installers. We do not accredit them.

Add more project detail (optional)

You choose whether to accept any quote. Read our installer checks and privacy notice.